BOLTON ONE LEISURE CENTRE, BOLTON

Waterproofing for a first-class £34 million design and build project; a joint venture between Bolton County Council, Bolton University and the NHS. Xypex is now the main contractor’s first-choice for all waterproofing projects.

 

THE CHALLENGE

To provide an effective, life-long waterproofing solution for a brand new ground level swimming pool amenities including a 25m deep-water pool, a shallow-water learner pool and associated tanks, plus a first floor suspended hydrotherapy pool.

 

THE XYPEX SOLUTION

Bolton One required robust waterproofing to all pool facilities. After considering (and initially specifying) other forms of waterproofing, Xypex was specified by the main contractor as a stand-alone solution due to it’s self-healing properties.

Xypex Admix C Series -Main swimming pool shell and balance tanks, trainer pool shell and balance tanks, suspended first-floor hydrotherapy pool

Xypex Concentrate – All joints

Xypex Patch’n Plug – Remedial waterproofing of existing overflow channels in a mixture of substrates including block work and mortar

Xypex Megamix I – Remedial waterproofing of existing overflow channels in a mixture of substrates including block work and mortar

 

THE RESULTS

The ease of installation and effectiveness of the Xypex waterproofing system has convinced the main contractor that Xypex is the first-choice waterproofing solution for future new-build and remedial projects.

 

DOWNLOADS

CASE STUDY - BOLTON ONE LEISURE CENTRE

WATER RETAINING

PROJECT TYPE

New build

PROJECT LOCATION

Bolton, Greater Manchester

PRODUCTS SPECIFIED

Admix

Concentrate

Patch'n Plug

Megamix I

Hydroswell Sealant

https://smrxypex.co.uk/wp-content/uploads/2018/03/admix.jpg
https://smrxypex.co.uk/wp-content/uploads/2018/03/concentrate.jpg
https://smrxypex.co.uk/wp-content/uploads/2018/03/patch-plug.jpg
https://smrxypex.co.uk/wp-content/uploads/2018/03/megamix.jpg